Question 1SSC CGL
medium

10 men can complete a project in 18 days. 12 women can complete the same project in 20 days, and 15 boys can complete it in 24 days. A combined team of 6 men, 10 women, and 9 boys is formed to execute a new project that is exactly 1.5 times the size of the original project. How many days will this combined team take to complete the new project?

Click any option to test your answer, or review the verified solution below.

Detailed Mathematical Solution

Step-by-step verified derivation with KaTeX equations

Correct Answer:B: 15 days

Let total work=LCM(10×18work = LCM(10 \times 18, 12×20, 15×24) = LCM(180, 240, 360) = 720 units.
Efficiencies:
• Man=720180=4Man = \frac{720}{180} = 4 units/day
• Woman=720240=3Woman = \frac{720}{240} = 3 units/day
• Boy=720360=2Boy = \frac{720}{360} = 2 units/day
Combined team (6M+10W+9B)=6×4+10×3+9×2=24+30+18=72(6M + 10W + 9B) = 6 \times 4 + 10 \times 3 + 9 \times 2 = 24 + 30 + 18 = 72 units/day.
New project=1.5×720=1080project = 1.5 \times 720 = 1080 units.
Time=108072=××15Time = \frac{1080}{72} = \times \times 15 days**.
Correct option: 15 days

Final ConclusionTherefore, the correct choice is B: 15 days
Verified 100% Accurate

Joru AI Exam Intelligence Studio

AI Memory Trick & Mnemonic

Exam Recall

Rapid cognitive retrieval rule to recall under high-pressure exam conditions for Efficiency and Work Rate.

LCM of (men×days, women×days, boys×days) gives total work in units.

Topper's Speed Method (AI Shortcut)

Speed Drill
Target: < 45s

How top 1% rankers bypass long textbook steps using composite ratios and mental arithmetic.

1

Compute LCM of all given (workers×days) products to set total work.

2

Derive per-person efficiency for each category.

3

Sum efficiencies for the mixed team and divide new work by combined rate.

Distractor Trap Analysis

Mistake Prevention
Trap Risk: 43%

Forensic analysis of why candidates mistakenly pick wrong distractor choices.

Pitfall & Trap Prevention: Requires LCM computation and multi-step efficiency conversion.

Exam Benchmark Specifications

Benchmark Time
45s
Target solving speed
Difficulty
medium
Exam tier rating
Depth
intermediate
Cognitive taxonomy
Target Exam
SSC CGL
Quantitative Aptitude

Core Concept & Theory Reference

Efficiency and Work Rate

Total work = constant units via LCM. Efficiency=workdaysEfficiency = \frac{work}{days}. Combined rate = sum of rates. Time=workrateTime = \frac{work}{rate}.