A, B, and C can complete a piece of construction work in 36, 45, and 60 days respectively. They started the work together, but B left 12 days before the completion of the work, and C left 8 days before the completion of the work. For how many days did the entire work last until it was fully completed?

Click any option to test your answer, or review the verified solution below.

Detailed Mathematical Solution

Step-by-step verified derivation with KaTeX equations

Correct Answer:B: 21 days

Take total work=LCM(36work = LCM(36,45,60) = 180 units.
Efficiencies: A=5A = 5, B=4B = 4, C=3C = 3 units/day.
Let total days = xx.
A works all xx days, B works (x−12)(x-12) days, C works (x−8)(x-8) days.
Equation: 5x+4(x−12)+3(x−8)=1805x + 4(x-12) + 3(x-8) = 180
⇒5x+4x−48+3x−24=180\Rightarrow 5x + 4x - 48 + 3x - 24 = 180
⇒12x−72=180⇒12x=252⇒x=21\Rightarrow 12x - 72 = 180 \Rightarrow 12x = 252 \Rightarrow x = 21.
Hence, the work lasted 21 days.

Final ConclusionTherefore, the correct choice is B: 21 days
Verified 100% Accurate

Joru AI Exam Intelligence Studio

AI Memory Trick & Mnemonic

Exam Recall

Rapid cognitive retrieval rule to recall under high-pressure exam conditions for Work with Variable Participation.

LCM gives total work; subtract absent days from total days to get individual work days.

Topper's Speed Method (AI Shortcut)

Speed Drill
Target: < 45s

How top 1% rankers bypass long textbook steps using composite ratios and mental arithmetic.

1

Instantly compute LCM and efficiencies.

2

Write equation with (x - early days) for those who left early.

3

Solve for x and verify with options.

Distractor Trap Analysis

Mistake Prevention
Trap Risk: 43%

Forensic analysis of why candidates mistakenly pick wrong distractor choices.

Pitfall & Trap Prevention: Requires setting up equation with variable working days for each person.

Exam Benchmark Specifications

Benchmark Time
45s
Target solving speed
Difficulty
medium
Exam tier rating
Depth
intermediate
Cognitive taxonomy
Target Exam
SSC CGL
Quantitative Aptitude

Core Concept & Theory Reference

Work with Variable Participation

LCM method: Total work = LCM of individual times. Efficiency = Total work / Time. Work done=Efficiency×Daysdone = Efficiency \times Days worked.